Shopping centre — Paris region
Building
Mission details
Mission
Criticality analysis of events — court-appointed expertise
Objectives
- Analysis of unitary and cumulative impacts of changes
- Analysis of delays attributable to the general contractor
Stakes
- 8-month delay on an initial 18-month schedule
- €15.5M on an initial €42M contract (37%).
Result
Reports submitted, proceedings in progress.