Argos Construction
FR / EN
Our expertise in action

References

66 completed missions

Ferroviaire France
Contract Management Infrastructure & Transport

Rail — France

Railway line

Mission details

Context

Numerous changes introduced by the Owner had given rise to incomplete amendments and erroneous pricing. Argos Construction's critical-path analysis allowed the amendments to be corrected, anticipated subsequent events and produced a new schedule and budget — culminating in a contract extension.

Mission

Claim for additional compensation

Objectives

  • Contractual analysis and reconstruction of disruptive events
  • Delay analysis and review of pricing
  • Drafting of the memorandum and assistance through to acceptance of the works

Stakes

  • Delay of 1 month and 2 weeks on a 4-month-and-2-week schedule
  • €2M on a €9.5M contract
Bâtiment industriel + process DOM TOM
Claim Management Industry

Industrial building + process — French Overseas

Industrial building

Mission details

Context

Numerous changes during design had generated a significant volume of additional studies, but the client felt the impact was confined to the detailed-design phase. Argos Construction's analysis demonstrated that the main impact was on the preliminary-design phase, justifying the full cost overruns and securing €1.2M of additional compensation on a €2.8M contract.

Mission

Claim for additional compensation — changes to the specifications

Objectives

  • Impact of changes on preliminary studies
  • Review and complement of cost-overrun pricing

Stakes

  • 6-month extension of the preliminary design studies
  • €1.2M of additional compensation on a €2.8M contract

Results

Settlement formalised by amendment for €1.2M

Centre Commercial Région parisienne
Disputes & Arbitration Building & Real Estate

Shopping centre — Paris region

Building

Mission details

Mission

Criticality analysis of events — court-appointed expertise

Objectives

  • Analysis of unitary and cumulative impacts of changes
  • Analysis of delays attributable to the general contractor

Stakes

  • 8-month delay on an initial 18-month schedule
  • €15.5M on an initial €42M contract (37%).

Results

Reports submitted, proceedings in progress.

Génie civil & Bâtiment IDF et PACA
Restructuring Building & Real Estate

Civil engineering & Building — Île-de-France and PACA

Diagnostic, claims, client disputes

Mission details

Context

Initially called in for a claim review, Argos Construction convinced the shareholder to place the subsidiary under ad hoc mandate rather than launching a hasty social plan. Two acquirers were found and, despite subsequent judicial liquidation, Argos's technical assistance allowed two major public works to be completed and creditors to be repaid in full.

Mission

Diagnostic, claims, client disputes

Objectives

  • Diagnostic and review of ongoing matters
  • Handling of claims and validation of bank facilities
  • Assistance with contract management and client disputes

Stakes

  • €50M revenue, 350 employees

Results

Creditors repaid

Gare de métro France
Contract Management Infrastructure & Transport

Metro station — France

Metro station

Mission details

Context

Awarded a €180M / 62-month contract for an underground metro station in the Paris region, the joint venture benefited from real-time contract management led by Argos Construction. This approach allowed issues to be addressed regularly with the Owner and a 15-month overall slippage to be managed without delay penalties.

Mission

Assistance to the joint-venture lead with contract management

Objectives

  • Set-up of a contractual and administrative database
  • Operation of management tools and traceability of works
  • Assistance with drafting correspondence and draft amendments

Stakes

  • 15-month time extension on an initial 62-month schedule
  • €20M on a €180M contract

Results

Amendments signed for 11.5 months of time extension and €17M; discussions ongoing

Terrassement plateforme France
Claim Management Industry

Earthworks platform — France

Industrial platform

Mission details

Context

Six months after the earthworks began, daily site tensions were preventing the team from calmly grasping the limits of the lump-sum contract. The factual status report drawn up by Argos Construction refocused energy on the high-stake issues and revitalised contract management, leading to a settlement on the claim for additional compensation.

Mission

Preparation of a claim for additional compensation

Objectives

  • Contractual analysis and status report
  • Determination of entitlement to time extension
  • Drafting of the claim for additional compensation

Stakes

  • Formalisation of the time entitlement "consumed" by the events and their consequences known as of 18 July 2016: 2.4 weeks
  • €1,359,569 (excl. tax) overrun versus the initial budget

Results

Claim for additional compensation finalised as of 18 July 2016

Complexe Hospitalier France
Disputes & Arbitration Building & Real Estate

Hospital complex — France

Technical trades

Mission details

Mission

Delay and cost impact analysis — court-appointed expertise (termination)

Objectives

  • Critical analysis of the opposing party's report and impact assessment
  • Report on the contractual situation

Stakes

  • €8.5M on a €32M contract (32%).

Results

To come.

BTP Rhône Alpes et PACA
Restructuring Building & Real Estate

Construction — Rhône-Alpes and PACA

Diagnostic, claims, client disputes

Mission details

Context

The Independent Business Review carried out by Argos Construction set the divestment strategy and persuaded the owner not to pursue a recovery plan that would have been personally risky. Talks with a potential buyer could then begin on a clean footing.

Mission

Diagnostic, claims, client disputes

Objectives

  • Diagnostic and business plan review under ad hoc mandate then receivership
  • Financial assistance and works-stoppage closures during the sale plan

Stakes

  • €45M revenue, 455 employees
Centre de formation France
Contract Management Building & Real Estate

Training centre — France

Real estate development

Mission details

Context

Engaged to deliver a €74M training centre in 20 months, the project is now running 21 months late with amendments for 17 months already signed. Argos Construction supports the developer in its dealings with a demanding Owner and a joint venture pursuing a tough contractual stance.

Mission

Contract management for the developer

Objectives

  • Set-up of a contractual database
  • Traceability of works and events
  • Assistance with drafting correspondence and amendments

Stakes

  • €74M (excl. tax) construction contract
  • 21-month delay in completion versus a 20-month schedule

Results

Amendments signed for 17 months of time extension and €9.5M; discussions ongoing