Claim Management
Environment & Urban Planning
Landscaped park development — Southern France
Landscaped park
Mission details
Context
After the claim for additional compensation was rejected at the general account stage, the small contractor referred the matter to the Administrative Court. Argos Construction's intervention as technical adviser alongside counsel helped secure €85k out of the €100k claimed.
Mission
Claim memorandum — draft final account
Objectives
- Justification of additional works and time extension
- Analysis of the impact on resource mobilisation
- Establishment of cost-overrun and damages pricing
Stakes
- 1-month time extension on an initial 5-month schedule
- €100k of additional compensation on a €200k contract
Results
Administrative Court ruling: €85k