Context

For a company member of a consortium holding a contract for nuclear power plants compliance upgrade (post-Fukushima): preparation of claim presenting disruptions during design phase and quantification of the extra costs and damages.

Mission

Claims Management

Objectives

  • Explanation and substantiation of disruptions experienced (delays in the transmission of input data, in the approval of design documents, etc.)
  • Quantum assessment

Stakes

  • Time for Completion: 7 years
  • Contract amount: € 56M
  • Extra costs and damages 4 years after the Contract date: € 19M

Result

The ARGOS report enabled the Contractor to conduct amicable negotiations with its client, resulting in an addendum.