Complexe industriel – en Afrique du Nord
Disputes & Arbitration Industry

Industrial complex – Phosphoric acid production

Gaseous waste treatment system

Mission details

Context

Pour le Client Maître d’Ouvrage, dans le cadre d’un litige avec le Constructeur d’un projet clé en main en Afrique du Nord, pour la mise en place d’unités de traitement des pollutions de deux usines en production : élaboration d’une analyse délais, établissement du Quantum comprenant l’analyse des demandes de rémunération complémentaires du Constructeur (environ 23 M€) et l’élaboration de la contre-réclamation du Client ;

Mission

Disputes & Arbitration

Objectives

  • Delay analysis according to the As Planned versus As Built Windows Analysis’ method;
  • Independent critical review of the Contractor’s claims;
  • Assessment of Quantum and damages suffered by the Client;

Stakes

  • Turnkey design and build contract worth €46.8M excl. tax to renovate operational industrial units;
  • Delays between 2 and 14 months depending on the production unit, for an initial one-year schedule;
  • Contractor’s claim of 23 M€ excl. tax.

Results

ARGOS’ reports enabled the Client to find an amicable settlement

Bâtiment industriel + process DOM TOM
Claim Management Industry

Industrial building + process — French Overseas

Industrial building

Mission details

Context

Numerous changes during design had generated a significant volume of additional studies, but the client felt the impact was confined to the detailed-design phase. Argos Construction's analysis demonstrated that the main impact was on the preliminary-design phase, justifying the full cost overruns and securing €1.2M of additional compensation on a €2.8M contract.

Mission

Claim for additional compensation — changes to the specifications

Objectives

  • Impact of changes on preliminary studies
  • Review and complement of cost-overrun pricing

Stakes

  • 6-month extension of the preliminary design studies
  • €1.2M of additional compensation on a €2.8M contract

Results

Settlement formalised by amendment for €1.2M

Terrassement plateforme France
Claim Management Industry

Earthworks platform — France

Industrial platform

Mission details

Context

Six months after the earthworks began, daily site tensions were preventing the team from calmly grasping the limits of the lump-sum contract. The factual status report drawn up by Argos Construction refocused energy on the high-stake issues and revitalised contract management, leading to a settlement on the claim for additional compensation.

Mission

Preparation of a claim for additional compensation

Objectives

  • Contractual analysis and status report
  • Determination of entitlement to time extension
  • Drafting of the claim for additional compensation

Stakes

  • Formalisation of the time entitlement "consumed" by the events and their consequences known as of 18 July 2016: 2.4 weeks
  • €1,359,569 (excl. tax) overrun versus the initial budget

Results

Claim for additional compensation finalised as of 18 July 2016

Tuyauterie industrielle Rhône Alpes et PACA
Restructuring Industry

Industrial pipework — Rhône-Alpes and PACA

Ongoing works, client management (receivership)

Mission details

Context

Faced with major subcontracting issues, Argos Construction proposed a method for assessing the major ongoing projects across all branches, accelerating entry into receivership. Technical assistance during the sale plan then enabled the closure of the remaining unsettled matters.

Mission

Diagnostic and steering during receivership

Objectives

  • Diagnostic and review of ongoing matters
  • Handling of claims and validation of bank facilities
  • Dispute management and works-stoppage closures

Stakes

  • €55M, 450 employees
Laveries Maghreb
Disputes & Arbitration Industry

Laundries — Maghreb

Engineering

Mission details

Mission

Limited external opinion for the Architect

Objectives

  • Analysis of changes and disruptions per contract
  • Summary note on schedule and financial impacts

Stakes

  • 14-month delay on an initial 22-month schedule
  • €60.1M (eq.) on a €57.4M (eq.) contract.

Results

To come.

Four industriel France
Disputes & Arbitration Industry

Industrial furnace — France

Building

Mission details

Objectives

  • Analysis of the impact of changes and disruptions on execution
  • Defects analysis and presentation of technical solutions

Stakes

  • €3.9M on a €3.7M contract.

Results

Amicable negotiation.