Infrastructures sportives et routières
Disputes & Arbitration Infrastructure & Transport

Sports and transport infrastructures

Construction and renovation of a sports complex in Africa

Mission details

Context

Dans le cadre d’un arbitrage CCI, pour un groupement d’entreprises françaises titulaire de plusieurs contrats de travaux pour la construction d’infrastructures routières et de complexes omnisports en Afrique, dont le montant total des marchés objets du litige s’élève à 57 M€., la réalisation d’une expertise sur le Quantum présentant un montant d’environ 32 M€ et l’analyse de la demande reconventionnelle de la partie adverse.

Mission

Disputes & Arbitration

Objectives

  • Review and analysis of procedural documents (invoices, statements of account, general ledger, transfer orders);
  • Assessment of Quantum of the outstanding payments and damages suffered;
  • Analysis of and responses to the opposing party's expert reports;
  • Hearings’ participation.

Stakes

  • High volume of contracts (100 contracts and purchase orders) across three distinct projects;
  • Total outstanding payments of 24,7M€ eq;
  • Total moratory and compensatory interest of 31,5 M€.

Result

NA

Métro
Claim Management Infrastructure & Transport

Metro Line

Smoke Extraction Ventilation of a Metro Line

Mission details

Context

In the context of a program to increase train capacity (from 26 m to 52 m) and modernize a metro line, a company was entrusted with the ventilation and smoke extraction works for 17 stations and 12 inter-station shafts, under an initial contract supplemented by an additional contract, for a total amount of €7.0 M excl. VAT.

The execution of the contract was severely disrupted by events beyond the contractor's control, including in particular the discovery of asbestos in stations and shafts, changes to safety standards imposed by State authorities, and multiple instances of late handovers. These disruptions resulted in a fundamental upset to the project's economics and significant delays to both partial and overall completion milestones.
Argos Construction acted as expert in support of Colas Rail in connection with its claim for additional compensation.

Mission

Claim Management

Objectives

  • Analyse and quantify the external disruptions and their consequences on the contractor's schedule and costs;
  • Demonstrate the fundamental upset to the project's economics, justifying the claim for additional compensation;
  • Assess and value the additional costs arising from the disruptions and the acceleration measures proposed at the Client's request.

Stakes

  • Total contract value: € 7.0 M excl. VAT (initial contract € 4.9 M + amendment no. 1 € 0.5 M + additional contract €1.6M)
  • Initial overall completion period: 54 months;
  • Delays justified by disruptions: 47.6 months on the overall completion period;
  • Main disruptive events: discovery of asbestos in shafts and stations, modification of the system's safety level, late handovers (AGI cabinets, cable trays, electrical supplies), requests from the Quality Assurance Inspector (unit-by-unit commissioning, shaft throttling), additional works via 15 Variation Orders (€ 1.2M excl. VAT, representing 17% of the total contract value).
LGV
Claim Management Infrastructure & Transport

High-Speed Rail Line (HSL)

High-Speed Rail Line (HSL) Design and Construction of Railway Equipment (>100 km)

Mission details

Context

The project involves the design and construction of railway equipment (track, overhead line equipment and construction base) for a High-Speed Rail Line, entrusted to a joint venture under a lump-sum contract.
The construction site, spanning 106 km divided into 14 distinct zones, was disrupted by numerous events beyond the Joint Venture's control (defective input data, hold points, sleeper rejection rates, acts of vandalism), forcing the Joint Venture to continuously adapt its plant and labour resources.
Despite these disruptions, the line energisation date was met.
Argos Construction acted as expert in support of the Joint Venture in connection with its claim for additional compensation for fundamental upset to the contract's economics.

Mission

Claim Management

Objectives

  • Analyse and quantify the external disruptions suffered by the Joint Venture during contract execution;
  • Demonstrate the fundamental upset to the project's economics and the undermining of the conditions under which the tender was prepared;
  • Compile and value the Joint Venture's claim submission for additional compensation.

Stakes

  • Contract value: €179.6M (excl. VAT) (lump sum) for 106 km of line;
  • Overall contract period: 52 months, with partial milestone no. 1 (Track and Overhead Line) of 46 months;
  • Critical schedule constraint: compliance with the line energisation date, a critical milestone conditioning the works of the Signalling package (outside the contract);
  • Main disruptive events: late and erroneous transmission of input data, definition and release of Z-50 and Z-20 hold points, unsubstantiated variation and anomaly notices, increase in sleeper rejection rates, acts of vandalism, remedial works following an accident.
Viaduc de Rennes
Claim Management Infrastructure & Transport

Viaduct Construction

A viaduct construction (2,395m) in Rennes

Mission details

Context

As part of the construction of Rennes' second automated metro line (Line B, 13.6 km), the Client entrusted a joint venture with the execution of Package No. 4, comprising a 2,395 m prestressed concrete viaduct with precast segmental construction.
The contract was severely disrupted by the continuous modification of input data (operational loads, Siemens rolling stock).
These modifications gave rise to an entitlement to a 25-month extension of time and a fundamental upset to the contract's economics.
Argos Construction acted as expert in support of the Joint Venture to carry out an independent review of the Explanatory Dossiers and the Technical and Financial Acceleration Proposal in the context of amicable negotiations with the Client.

Mission

Claim Management

Objectives

  • Carry out a limited and independent review of the 7 Explanatory Dossiers submitted by the Joint Venture (additional design, methodology and construction costs);
  • Analyse and validate the Technical and Financial Proposal for acceleration of the works;
  • Identify financial impacts not presented by the Joint Venture and assess a realistic amount that could form the basis of a prompt amicable settlement.

Stakes

  • Contract value: €39M (excl. VAT) (final and revisable unit prices);
  • Contractual duration: 39 months;
  • Total entitlement to extension of time: 25.0 months (i.e. 64% of the initial duration);
  • Main disruptive events: late transmission and continuous modification of input data over 20 months, modification of the launching girder, geometric modifications to piers and segments, modification of the prestressing scheme (+4.3 months on segment installation), disruptions at the CROUS site;
  • Total claim by the Joint Venture: €26.9M (excl. VAT) (Explanatory Dossiers + acceleration);
  • Amount partially accepted by the Client during negotiations: €4.8M (excl. VAT) (Explanatory Dossiers) + €3.4M (excl. VAT) (acceleration), totalling €8.3M (excl. VAT).
Gare de métro en région parisienne
Claim Management Infrastructure & Transport

Metro Station in the Greater Paris area

Fit-Out of a Railway Station

Mission details

Context

As part of an all-trade (TCE) fit-out contract for a railway station, with a value of €80 million and a duration of 47 months, the contractor experienced major events during both the detailed design phase and the construction works, resulting in a 33-month delay to the project completion.

Mission

Argos Construction was appointed by the contractor to (i) prepare a claim report to support its request for an extension of time and additional compensation, and (ii) assist in defending the claim throughout the negotiation phase.

Objectives

  • Analysis of contractual, technical, and administrative documents
  • Review of contemporaneous project records
  • Preparation of a claim report analyzing the causes of delays and their financial consequences
  • Analysis of opposing arguments and preparation of technical notes/reports in response
  • Participation in technical review and negotiation meetings to support our work

Stakes

  • €35 million in additional costs and damages claimed by the contractor

Result

Execution of a contract amendment granting the contractor a 33-month extension of time and additional compensation of approximately €20 million

Gare de métro en région parisienne
Claim Management Infrastructure & Transport

Metro Station in the Greater Paris area

Fit-Out of a Railway Station

Mission details

Context

As part of an all-trade (TCE) fit-out contract for a railway station, with a value of €53 million and a duration of 50 months, the contractor experienced major events during both the detailed design phase and the construction works, resulting in a 9-month delay to the project completion.

Mission

Argos Construction was appointed by the contractor to carry out an analysis of the causes of delay.

Objectives

  • Analysis of contractual, technical, and administrative documents
  • Review of contemporaneous project records
  • Preparation of a report analyzing the causes of delays (method used: Time Impact Analysis)

Stakes

  • €10 million in additional costs and damages claimed by the contractor (including a proposed acceleration plan)
  • €2 million in delay penalties incurred
Tramway Centre de la France
Claim Management Infrastructure & Transport

Tramway — Central France

Tramway line

Mission details

Context

Engaged to audit the contractual management database of a tramway project already showing 18% cost overruns and delays threatening penalties, Argos Construction exposed process and methodology weaknesses. By demonstrating that the contractor was not solely responsible for the delays, penalties were avoided and a claim for additional compensation could even be presented.

Mission

Audit of the contract information system

Objectives

  • Analysis of contract documents and information sources
  • Review of pricing and claim topics
  • Status report with recommendations

Stakes

  • Justification of cost overruns of €6M on a €34M contract

Result

Team awareness raised; tools improved and rolled out for tracking disruptions, enabling a claim for additional compensation

Tramway Sud de la France
Contract Management Infrastructure & Transport

Tramway — Southern France

Tramway line

Mission details

Context

Brought in on a project already running twelve months late, Argos Construction established a clear view of the situation and prepared the elements of the claim, leading to financial compensation awarded by the court. The case illustrates what proactive contract management and the right tools could have prevented.

Mission

Contractual analysis and claim

Objectives

  • Analysis of contract documents and the technical file
  • Review of pricing and assistance with drafting the claim memorandum
  • Assistance with defending the claim

Stakes

  • 390 days of time extension on an initial 22-month schedule
  • €174,940 on a €1.9M contract
Adduction Eau Potable Maghreb
Disputes & Arbitration Infrastructure & Transport

Drinking water supply — Maghreb

Civil works

Mission details

Mission

Review of compensation claims — water main (ICC arbitration)

Objectives

  • Delay analysis per structure and quantum of cost overruns
  • Drafting and presentation of the memorandum
  • Participation in arbitral hearings (ICC)

Stakes

  • Delay of 19.3 months on an initial 27-month schedule
  • €128M on a €108M contract

Result

To come.