Immeubles de Bureaux Sud de la France
Claim Management Building & Real Estate

Office buildings — Southern France

Office buildings

Mission details

Context

On a painting contract where any change weighs directly on labour, late hand-over of work areas had stretched the schedule by 37% — but the team, inexperienced in contract management, could not substantiate it. Argos Construction's presentation of the claim convinced the Owner of the contractor's rigour and led to new contracts.

Mission

Preparation of a claim for additional compensation

Objectives

  • Justification of work-window shifts caused by disruptions
  • Establishment of cost-overrun and damages pricing

Stakes

  • 3-month extension on an initial 8-month schedule
  • €100k of additional compensation on a €300k contract

Result

Claim initially rejected. Assistance with case follow-up and management of forfeiture deadlines. Settlement negotiated at €60k

Adduction Eau Potable Maghreb
Disputes & Arbitration Infrastructure & Transport

Drinking water supply — Maghreb

Civil works

Mission details

Mission

Review of compensation claims — water main (ICC arbitration)

Objectives

  • Delay analysis per structure and quantum of cost overruns
  • Drafting and presentation of the memorandum
  • Participation in arbitral hearings (ICC)

Stakes

  • Delay of 19.3 months on an initial 27-month schedule
  • €128M on a €108M contract

Result

To come.

Travaux publics Alsace et Allemagne
Restructuring Infrastructure & Transport

Public works — Alsace and Germany

Diagnostic

Mission details

Context

The Independent Business Review carried out by Argos Construction defined a three-year business plan, but the funding requirement proved too high for the shareholder, who withdrew. The company entered receivership, leading to two separate sale plans for the utilities and earthworks businesses.

Mission

Diagnostic

Objectives

  • Economic and financial diagnostic (organisation, risks, business plan)
  • Funding-needs study and information memorandum for sale

Stakes

  • €150M revenue, 850 employees
Tramway Sud-Est de la France
Contract Management Infrastructure & Transport

Tramway — South-East France

Tramway line

Mission details

Context

Setting up contract management from the outset made it possible to record every event and send regular reports to the Owner. Amendments and cost overruns were settled immediately, avoiding any dispute.

Mission

Preparatory review and claim memorandum

Objectives

  • Contractual analysis and identification of delay-related issues
  • Establishment of cost-overrun pricing
  • Preparation of the claim for additional compensation

Stakes

  • Schedule of 24 months versus an initial 20 months
  • €4M of additional compensation + €150k waiver of penalties on a €38M (excl. tax) contract
Aménagement parc paysager Sud de la France
Claim Management Environment & Urban Planning

Landscaped park development — Southern France

Landscaped park

Mission details

Context

After the claim for additional compensation was rejected at the general account stage, the small contractor referred the matter to the Administrative Court. Argos Construction's intervention as technical adviser alongside counsel helped secure €85k out of the €100k claimed.

Mission

Claim memorandum — draft final account

Objectives

  • Justification of additional works and time extension
  • Analysis of the impact on resource mobilisation
  • Establishment of cost-overrun and damages pricing

Stakes

  • 1-month time extension on an initial 5-month schedule
  • €100k of additional compensation on a €200k contract

Result

Administrative Court ruling: €85k

Route Maroc
Disputes & Arbitration Infrastructure & Transport

Road — Morocco

Public works

Mission details

Mission

Review of damages following contract termination (ICC arbitration)

Objectives

  • Review of contract documents and opinion on pricing
  • Participation in cross-examination before the Arbitral Tribunal

Stakes

  • €91M contract, claims of €40M.

Result

To come.

Constructeur Maisons individuelles Île-de-France
Restructuring Building & Real Estate

Single-family house builder — Île-de-France

Diagnostic and steering

Mission details

Context

At the guarantor's request, Argos Construction prepared the forecasts that supported a takeover as interim manager. The firm then guided the recovery over two years, co-building the action plan and operating the management dashboards.

Mission

Diagnostic and steering

Objectives

  • Operational and financial diagnostic
  • Development of dashboards and modelling tools

Stakes

  • €135M revenue, 55 employees
Ferroviaire France
Contract Management Infrastructure & Transport

Rail — France

Railway line

Mission details

Context

Numerous changes introduced by the Owner had given rise to incomplete amendments and erroneous pricing. Argos Construction's critical-path analysis allowed the amendments to be corrected, anticipated subsequent events and produced a new schedule and budget — culminating in a contract extension.

Mission

Claim for additional compensation

Objectives

  • Contractual analysis and reconstruction of disruptive events
  • Delay analysis and review of pricing
  • Drafting of the memorandum and assistance through to acceptance of the works

Stakes

  • Delay of 1 month and 2 weeks on a 4-month-and-2-week schedule
  • €2M on a €9.5M contract
Bâtiment industriel + process DOM TOM
Claim Management Industry

Industrial building + process — French Overseas

Industrial building

Mission details

Context

Numerous changes during design had generated a significant volume of additional studies, but the client felt the impact was confined to the detailed-design phase. Argos Construction's analysis demonstrated that the main impact was on the preliminary-design phase, justifying the full cost overruns and securing €1.2M of additional compensation on a €2.8M contract.

Mission

Claim for additional compensation — changes to the specifications

Objectives

  • Impact of changes on preliminary studies
  • Review and complement of cost-overrun pricing

Stakes

  • 6-month extension of the preliminary design studies
  • €1.2M of additional compensation on a €2.8M contract

Result

Settlement formalised by amendment for €1.2M