Contact us

Contact us
Argos Construction
FR / EN

References

Our expertise in action

Complexe industriel – en Afrique du Nord
Disputes & Arbitration Industry

Industrial complex – Phosphoric acid production

Gaseous waste treatment system

Mission details

Context

Pour le Client Maître d’Ouvrage, dans le cadre d’un litige avec le Constructeur d’un projet clé en main en Afrique du Nord, pour la mise en place d’unités de traitement des pollutions de deux usines en production : élaboration d’une analyse délais, établissement du Quantum comprenant l’analyse des demandes de rémunération complémentaires du Constructeur (environ 23 M€) et l’élaboration de la contre-réclamation du Client ;

Mission

Disputes & Arbitration

Objectives

  • Delay analysis according to the As Planned versus As Built Windows Analysis’ method;
  • Independent critical review of the Contractor’s claims;
  • Assessment of Quantum and damages suffered by the Client;

Stakes

  • Turnkey design and build contract worth €46.8M excl. tax to renovate operational industrial units;
  • Delays between 2 and 14 months depending on the production unit, for an initial one-year schedule;
  • Contractor’s claim of 23 M€ excl. tax.

Result

ARGOS’ reports enabled the Client to find an amicable settlement

Infrastructures sportives et routières
Disputes & Arbitration Infrastructure & Transport

Sports and transport infrastructures

Construction and renovation of a sports complex in Africa

Mission details

Context

Dans le cadre d’un arbitrage CCI, pour un groupement d’entreprises françaises titulaire de plusieurs contrats de travaux pour la construction d’infrastructures routières et de complexes omnisports en Afrique, dont le montant total des marchés objets du litige s’élève à 57 M€., la réalisation d’une expertise sur le Quantum présentant un montant d’environ 32 M€ et l’analyse de la demande reconventionnelle de la partie adverse.

Mission

Disputes & Arbitration

Objectives

  • Review and analysis of procedural documents (invoices, statements of account, general ledger, transfer orders);
  • Assessment of Quantum of the outstanding payments and damages suffered;
  • Analysis of and responses to the opposing party's expert reports;
  • Hearings’ participation.

Stakes

  • High volume of contracts (100 contracts and purchase orders) across three distinct projects;
  • Total outstanding payments of 24,7M€ eq;
  • Total moratory and compensatory interest of 31,5 M€.

Result

NA

Rénovation de silos à grains en Afrique occidentale
Disputes & Arbitration Industry

Grain Silos

Renovation of Grain Silos in West Africa

Mission details

Context

The project involves the renovation of 32 reinforced concrete cells (wheat silos) at a port in West Africa, entrusted to a joint venture composed of a French company and a local company.
The works were quickly disrupted by technical difficulties related to the mix design of the sprayed concrete, then brought to a standstill due to an unresolved issue of insufficient bearing capacity of the existing foundations.
In the absence of an agreement through conciliation, the Client terminated the contract, leading the Joint Venture to initiate arbitration proceedings before the ICC in Paris.
Argos Construction acted as quantum expert in support of the Joint Venture in order to analyse the claims of both parties.

Mission

Disputes & Arbitration

Objectives

  • Assess and defend the Joint Venture's claims in the context of the ICC arbitration;
  • Analyse and rebut the Client's counterclaims and the conclusions of the opposing expert;
  • Produce successive quantum reports in support of the submissions filed before the International Court of Arbitration.

Stakes

  • Contractual works duration: 17 months;
  • Net claim of the Joint Venture: ~€1.1M (incl. VAT) (after repayment of the mobilisation advance of €1.065M, on a gross loss of ~€2.87M);
  • Client's counterclaims: €32.1M (incl. VAT);
  • Key issues in dispute: whether the termination was wrongful, works stoppage linked to the existing foundations, non-conformity of the sprayed concrete with contractual requirements, liability for additional costs and delays.
Tour résidentielle à Varsovie
Disputes & Arbitration Building & Real Estate

Residential Tower

Residential tower in Warsaw (Poland)

Mission details

Context

The project involves the construction of a residential tower in Warsaw, Poland, under a lump-sum contract valued at €25.8M (excl. VAT). Following termination of the contract by the Client, an arbitration dispute arose between the two parties concerning the final account, contractual penalties, damages and the contractor's claims. Argos Construction acted as quantum expert in support of the contractor INSO, in order to analyse and value the company's counterclaim.

Mission

Disputes & Arbitration

Objectives

  • Analyse and respond to the Client's statement of claim on a line-by-line basis;
  • Assess and value the contractor's counterclaim (additional works, losses and damages, termination costs, interest);
  • Identify and demonstrate errors and omissions in the valuation carried out by the opposing party's expert.

Stakes

  • Contract value: ≈€25.8M — lump-sum contract;
  • Total gap between the parties' positions: over €17.5M;
  • Key issues in dispute: termination penalty (10% of the contract price), damages for delay (76 days), additional works arising from the Client's variations, payments to subcontractors, defective works, loss of margin on unexecuted works.
Complexe immobilier en Afrique du Nord
Disputes & Arbitration Building & Real Estate

Real Estate Complex in North Africa

Construction and rehabilitation of a Real Estate Complex in North Africa

Mission details

Context

As part of an ICC arbitration between a Turkish contractor and an Algerian project owner, Argos Construction acted as an independent expert.
The project under arbitration is located in Algeria and involves a mixed development combining new construction and refurbishment to create a real estate complex including a shopping center, a hotel, office spaces, an underground parking facility, and a conference center.
The total construction cost amounts to €100 million, with an initial execution period of 27 months.
The project experienced a delay extension of 22 months, and the parties were unable to determine their respective responsibilities.Describe the project context in 3 to 5 sentences: nature of the project, stakeholders, issues encountered and the value added by Argos Construction.

Mission

Argos Construction was appointed by the contractor (the respondent) as an independent expert to provide an opinion on the causes of the project delays and their financial consequences.

Objectives

  • Analysis of contractual, technical, and administrative documents
  • Review of contemporaneous project records
  • Preparation of a report analyzing the causes of delays and their financial impact
  • Review of opposing expert reports and preparation of rebuttal reports
  • Participation in arbitration hearings to support our findings

Stakes

  • €30 million in additional costs and damages claimed by the contractor
  • €40 million in damages claimed by the project owner
Construction de 3 bâtiments et 38 villas à Ajaccio
Disputes & Arbitration Building & Real Estate

Buildings and Villas in Ajaccio

Construction of 3 Buildings and 38 Villas in Ajaccio

Mission details

Context

The project involves the construction of 3 buildings comprising 121 residential units and 2 commercial units, together with 38 villas, located in Ajaccio.
Works commenced in early 2023 before being suspended in July of the same year.
Argos Construction intervened, from late 2025, in the capacity of ad hoc administrator to assist the guarantor (GFA) in fulfilling its obligation to complete the works.

Mission

E.g.: Contract Management

Objectives

  • Take all decisions necessary for the management and completion of the programme;
  • Redefine the programme;
  • Assess the works and interventions remaining to be carried out;
  • Prepare a projected financial statement;
  • Submit the amended building permit application;
  • Procure and supervise, acting as substitute project owner specifically responsible for completion, all necessary works;
  • Audit the purchasers' accounts;
  • Arrange for formal certification of programme completion;
  • Organise the handover and acceptance process;
  • Settle the final accounts with the contractors.

Stakes

  • Duration of remaining works: 40 months;
  • Value of remaining works: ~€ 20 M excl. VAT.
Complexe Hôtelier Maroc
Disputes & Arbitration Building & Real Estate

Hotel complex — Morocco

Building

Mission details

Mission

Critical path analysis — hotel complex (3 hotels, 800 rooms, 22 ha)

Objectives

  • Contractual and technical delay analysis
  • Compliance issues analysis
  • Hearing preparation and advocacy

Stakes

  • Delay of at least 5.5 months on an initial 14-month schedule
  • €8M plus interest

Result

Reports submitted; amicable settlement reached

Adduction Eau Potable Maghreb
Disputes & Arbitration Infrastructure & Transport

Drinking water supply — Maghreb

Civil works

Mission details

Mission

Review of compensation claims — water main (ICC arbitration)

Objectives

  • Delay analysis per structure and quantum of cost overruns
  • Drafting and presentation of the memorandum
  • Participation in arbitral hearings (ICC)

Stakes

  • Delay of 19.3 months on an initial 27-month schedule
  • €128M on a €108M contract

Result

To come.

Route Maroc
Disputes & Arbitration Infrastructure & Transport

Road — Morocco

Public works

Mission details

Mission

Review of damages following contract termination (ICC arbitration)

Objectives

  • Review of contract documents and opinion on pricing
  • Participation in cross-examination before the Arbitral Tribunal

Stakes

  • €91M contract, claims of €40M.

Result

To come.