Promoteur privé Grand Projet Bâtiment Monaco
Disputes & Arbitration Building & Real Estate

Private developer — Major building project — Monaco

Building

Mission details

Mission

Technical advisor to the Owner — amicable expertise

Objectives

  • Analysis of the general contractor's claim files
  • Review of pricing and conclusions

Stakes

  • 6-month delay on an initial 56-month schedule
  • €20M on a €300M contract.

Result

Amicable negotiation.

Travaux de revêtements de sol Sud de la France
Restructuring Building & Real Estate

Floor covering works — Southern France

Technical assistance

Mission details

Context

Engaged to validate the opportunity of acquiring a company with complementary activities, Argos Construction assessed costs before and after the takeover and prepared the budget forecast based on the existing order book.

Mission

Technical assistance — review of the situation during acquisition

Objectives

  • Review of organisation and cost structure
  • Review of forecast margins, customer accounts and budget

Stakes

  • €5.5M revenue, 37 employees
Construction d'un échangeur routier
Claim Management Infrastructure & Transport

Road interchange construction

Civil works

Mission details

Context

With the works completed but acceptance refused due to leaks, the joint venture had presented a €9M claim covering 17 months of delay. Argos Construction's analysis distinguished 11 compensable months, 3 excusable but non-compensable months and 3 months attributable to the contractor, leading to partial admissibility of around €500k.

Mission

Report in response to the joint venture's claim memorandum

Barrages France Maghreb
Disputes & Arbitration Infrastructure & Transport

Dams — France and Maghreb

Civil works

Mission details

Mission

Review of financial claim files — dam

Objectives

  • Analysis of contractual elements and pricing of cost overruns
  • Drafting of the memorandum and contract-management follow-up

Stakes

  • 20-month delay on an initial 33-month schedule
  • €78M on a €159M contract.

Result

€28M for a recommendation between €28M and €40M.

Travaux publics Île-de-France
Restructuring Infrastructure & Transport

Public works — Île-de-France

Ad hoc mandate and receivership

Mission details

Context

Threatened with the withdrawal of bank facilities following a drop in business and weak management control, the company entered receivership. The Independent Business Review and forecasts prepared by Argos Construction for its seven subsidiaries clarified the situation and supported the divestment.

Mission

Ad hoc mandate then receivership

Objectives

  • Preparation of forecasts and control of receivable mobilisations
  • Review of customer accounts and opinions on contract terminations

Stakes

  • €69M, 60 employees
Ferroviaire France
Claim Management Infrastructure & Transport

Rail — France

Railway line

Mission details

Context

Faced with a €7M penalty demand from the Owner, the contractor was claiming €16M of additional compensation. Argos Construction's detailed analysis showed that the changes imposed by the Owner itself were the cause of the delays, allowing the penalties to be set aside.

Mission

Preparation of a claim for additional compensation — general account

Objectives

  • Contractual analysis and reconstruction of disruptive events
  • Delay analysis and financial impacts
  • Drafting of the additional-compensation memorandum

Stakes

  • Phase 1: 14-day delay on an initial 147 days; Phase 2: 35-day delay on an initial 91 days; Phase 3: 0 days on an initial 112 days
  • €8M on a €50M contract

Result

Out-of-court settlement

Régénération voies France
Disputes & Arbitration Infrastructure & Transport

Track regeneration — France

Transport

Mission details

Mission

Claim for additional compensation

Objectives

  • Quantification and presentation of damages
  • Assistance with defence and participation in meetings
  • Drafting of supplementary memoranda

Stakes

  • 49-day delay on an initial 8-month schedule
  • €7M on a €51M contract.

Result

To come.

Tuyauterie industrielle Rhône Alpes et PACA
Restructuring Industry

Industrial pipework — Rhône-Alpes and PACA

Ongoing works, client management (receivership)

Mission details

Context

Faced with major subcontracting issues, Argos Construction proposed a method for assessing the major ongoing projects across all branches, accelerating entry into receivership. Technical assistance during the sale plan then enabled the closure of the remaining unsettled matters.

Mission

Diagnostic and steering during receivership

Objectives

  • Diagnostic and review of ongoing matters
  • Handling of claims and validation of bank facilities
  • Dispute management and works-stoppage closures

Stakes

  • €55M, 450 employees
Hôpital Sud de la France
Claim Management Building & Real Estate

Hospital — Southern France

Hospital

Mission details

Context

Following Argos Construction's intervention, which restored balance between the Owner and the contractor wrongly identified as the source of the delays on this multi-trade project, a claim for additional compensation could be presented and defended.

Mission

Claim for additional compensation — final account

Objectives

  • Reconstruction of disruptions and substantiation of the time extension
  • Analysis of impact on resource mobilisation
  • Establishment of cost-overrun and damages pricing

Stakes

  • 23-month time extension on an initial 25-month schedule
  • €0.8M of additional compensation on a €3M contract

Result

Time extension formalised (delay penalties lifted) and settlement at €0.4M