Building refurbishment
Buildings
Mission details
Context
The conversion of this Parisian building into a 5-star hotel (€6M, 14 months) suffered a 7-month delay across all trades, entirely due to late input data and constant changes outside the joint venture's control. Argos Construction prepared the claim memorandum for €1.2M of cost overruns, while the Owner intends to apply €860k in delay penalties.
Mission
Preparation of a claim for additional compensation
Objectives
- Analysis of contract documents and contemporaneous records
- Analysis of cumulative delay impacts
- Quantification of cost overruns and drafting of the memorandum
Stakes
- 7-month delay on an initial 14-month schedule (+50%)
- €1.2M on an initial €6M contract (20%)