Training centre — France
Real estate development
Mission details
Context
Engaged to deliver a €74M training centre in 20 months, the project is now running 21 months late with amendments for 17 months already signed. Argos Construction supports the developer in its dealings with a demanding Owner and a joint venture pursuing a tough contractual stance.
Mission
Contract management for the developer
Objectives
- Set-up of a contractual database
- Traceability of works and events
- Assistance with drafting correspondence and amendments
Stakes
- €74M (excl. tax) construction contract
- 21-month delay in completion versus a 20-month schedule
Result
Amendments signed for 17 months of time extension and €9.5M; discussions ongoing