High-speed rail line — France
TGV line
Mission details
Context
Despite significant disruptions, the joint venture in charge of track-laying and overhead-line works (€200M) completed the project without jeopardising the train commissioning date. Argos Construction's analysis brought to light critical disruptions previously unidentified, allowing more than €10M in delay penalties to be challenged.
Mission
Claim for additional compensation relating to disruptions
Objectives
- Delay analysis and substantiation of entitlements
- Review and complement of cost-overrun pricing
- Drafting of the memorandum to be attached to the draft final account
Stakes
- 6 months of time extension to be substantiated
- €10M of delay penalties
- €30M of cost overruns
Results
Under discussion