Hospital — Southern France
Hospital
Mission details
Context
Six months after start-up, the earthworks/utilities contractor was being blamed for delays and held responsible for every site contingency. By bringing the issues back to the facts and clarifying each party's rights and duties, Argos Construction's intervention secured a time extension with no delay penalties.
Mission
Contract management
Objectives
- Contractual follow-up and traceability of disruptions
- Management of deadlines and service orders
- Training of the team in good contractual practice
Stakes
- 23-month time extension on an initial 25-month schedule
- €0.8M of additional compensation on a €3M contract
Result
Time extension formalised (delay penalties lifted) and settlement of €0.4M