References

10 completed missions

Complexe Hôtelier Maroc
Disputes & Arbitration Building & Real Estate

Hotel complex — Morocco

Building

Mission details

Mission

Critical path analysis — hotel complex (3 hotels, 800 rooms, 22 ha)

Objectives

  • Contractual and technical delay analysis
  • Compliance issues analysis
  • Hearing preparation and advocacy

Stakes

  • Delay of at least 5.5 months on an initial 14-month schedule
  • €8M plus interest

Results

Reports submitted; amicable settlement reached

Centre Commercial Région parisienne
Disputes & Arbitration Building & Real Estate

Shopping centre — Paris region

Building

Mission details

Mission

Criticality analysis of events — court-appointed expertise

Objectives

  • Analysis of unitary and cumulative impacts of changes
  • Analysis of delays attributable to the general contractor

Stakes

  • 8-month delay on an initial 18-month schedule
  • €15.5M on an initial €42M contract (37%).

Results

Reports submitted, proceedings in progress.

Complexe Hospitalier France
Disputes & Arbitration Building & Real Estate

Hospital complex — France

Technical trades

Mission details

Mission

Delay and cost impact analysis — court-appointed expertise (termination)

Objectives

  • Critical analysis of the opposing party's report and impact assessment
  • Report on the contractual situation

Stakes

  • €8.5M on a €32M contract (32%).

Results

To come.

Siège social France
Disputes & Arbitration Building & Real Estate

Corporate headquarters — France

Building refurbishment

Mission details

Mission

Final account analysis — weather-tight stage

Objectives

  • Analysis of design changes and time entitlements
  • Review of the general contractor's claims and Architect's opinion
  • Analysis of the account line items

Stakes

  • 6-month delay on an initial 2-year schedule
  • €5M on a €11M contract (32%).

Results

To come.

Promoteur privé Grand Projet Bâtiment Monaco
Disputes & Arbitration Building & Real Estate

Private developer — Major building project — Monaco

Building

Mission details

Mission

Technical advisor to the Owner — amicable expertise

Objectives

  • Analysis of the general contractor's claim files
  • Review of pricing and conclusions

Stakes

  • 6-month delay on an initial 56-month schedule
  • €20M on a €300M contract.

Results

Amicable negotiation.

Tour résidentielle Pologne
Disputes & Arbitration Building & Real Estate

Residential tower — Poland

Building

Mission details

Mission

Delay and quantum expertise — ICC arbitration (termination)

Objectives

  • Analysis of disruptive events and damages
  • Review of the Owner's claim
  • Hearing advocacy (in English)

Stakes

  • €10M on a €25M contract (i.e. 40% of the contract amount).

Results

Awaiting ruling.

Centre Médical Qatar
Disputes & Arbitration Building & Real Estate

Medical centre — Qatar

Building

Mission details

Mission

Independent opinion on delay analysis and estimation of cost overruns

Objectives

  • Analysis of documentation and strategy
  • Summary note on methodology and delay risks

Stakes

  • 25-month delay on an initial 15-month schedule
  • €197.7M (eq.) on a €268.4M (eq.) contract.

Results

To come.

Bureaux Algérie
Disputes & Arbitration Building & Real Estate

Offices — Algeria

Building

Mission details

Objectives

  • Report in response to the opposing expert on design and construction delays at the date of termination

Stakes

  • The general contractor presented a claim of €70.7M (eq.), or 141% of the initial contract amount
  • The Owner also filed counterclaims totalling €13.1M (eq.).

Results

The arbitrators confirmed that termination of the general contractor's contract was well founded and ordered the Owner to pay 11% of its claim.

Complexe immobilier
Disputes & Arbitration Building & Real Estate

Real estate complex

Building

Mission details

Mission

Independent expert appointed by the builder — analysis of delay causes and financial consequences (arbitration)

Stakes

  • 22 months of time extension
  • €30M of cost overruns and damages claimed by the builder
  • €40M of damages alleged by the Owner

Results

/.