Road interchange construction
Civil works
Mission details
Context
With the works completed but acceptance refused due to leaks, the joint venture had presented a €9M claim covering 17 months of delay. Argos Construction's analysis distinguished 11 compensable months, 3 excusable but non-compensable months and 3 months attributable to the contractor, leading to partial admissibility of around €500k.
Mission
Report in response to the joint venture's claim memorandum