Tramway — Southern France
Tramway line
Mission details
Context
Brought in on a project already running twelve months late, Argos Construction established a clear view of the situation and prepared the elements of the claim, leading to financial compensation awarded by the court. The case illustrates what proactive contract management and the right tools could have prevented.
Mission
Contractual analysis and claim
Objectives
- Analysis of contract documents and the technical file
- Review of pricing and assistance with drafting the claim memorandum
- Assistance with defending the claim
Stakes
- 390 days of time extension on an initial 22-month schedule
- €174,940 on a €1.9M contract