Our expertise in action

References

23 completed missions

Infrastructures ferroviaires & routières France
Disputes & Arbitration Infrastructure & Transport

Rail & road infrastructure — France

Transport

Mission details

Mission

Delay impact analysis — litigation on behalf of the Architect

Objectives

  • Determination of works performed (base contract vs. additional)
  • Assistance to counsel and report advocacy
  • Drafting of reports and supplementary notes

Stakes

  • 6-month delay on an initial 9.5-month schedule
  • €2,526k on a €9.66M contract.

Results

To come.

Promoteur privé Grand Projet Bâtiment Monaco
Disputes & Arbitration Building & Real Estate

Private developer — Major building project — Monaco

Building

Mission details

Mission

Technical advisor to the Owner — amicable expertise

Objectives

  • Analysis of the general contractor's claim files
  • Review of pricing and conclusions

Stakes

  • 6-month delay on an initial 56-month schedule
  • €20M on a €300M contract.

Results

Amicable negotiation.

Barrages France Maghreb
Disputes & Arbitration Infrastructure & Transport

Dams — France and Maghreb

Civil works

Mission details

Mission

Review of financial claim files — dam

Objectives

  • Analysis of contractual elements and pricing of cost overruns
  • Drafting of the memorandum and contract-management follow-up

Stakes

  • 20-month delay on an initial 33-month schedule
  • €78M on a €159M contract.

Results

€28M for a recommendation between €28M and €40M.

Régénération voies France
Disputes & Arbitration Infrastructure & Transport

Track regeneration — France

Transport

Mission details

Mission

Claim for additional compensation

Objectives

  • Quantification and presentation of damages
  • Assistance with defence and participation in meetings
  • Drafting of supplementary memoranda

Stakes

  • 49-day delay on an initial 8-month schedule
  • €7M on a €51M contract.

Results

To come.

Tunnel France
Disputes & Arbitration Infrastructure & Transport

Tunnel — France

Civil works

Mission details

Mission

Delay analysis and review of pricing — tunnel

Objectives

  • Review of the existing analysis and delay analysis
  • Preparation and drafting of the corresponding memorandum

Stakes

  • €4.8M on a €130M contract.

Results

Report submitted.

Tour résidentielle Pologne
Disputes & Arbitration Building & Real Estate

Residential tower — Poland

Building

Mission details

Mission

Delay and quantum expertise — ICC arbitration (termination)

Objectives

  • Analysis of disruptive events and damages
  • Review of the Owner's claim
  • Hearing advocacy (in English)

Stakes

  • €10M on a €25M contract (i.e. 40% of the contract amount).

Results

Awaiting ruling.

Laveries Maghreb
Disputes & Arbitration Industry

Laundries — Maghreb

Engineering

Mission details

Mission

Limited external opinion for the Architect

Objectives

  • Analysis of changes and disruptions per contract
  • Summary note on schedule and financial impacts

Stakes

  • 14-month delay on an initial 22-month schedule
  • €60.1M (eq.) on a €57.4M (eq.) contract.

Results

To come.

Centre Médical Qatar
Disputes & Arbitration Building & Real Estate

Medical centre — Qatar

Building

Mission details

Mission

Independent opinion on delay analysis and estimation of cost overruns

Objectives

  • Analysis of documentation and strategy
  • Summary note on methodology and delay risks

Stakes

  • 25-month delay on an initial 15-month schedule
  • €197.7M (eq.) on a €268.4M (eq.) contract.

Results

To come.

Bureaux Algérie
Disputes & Arbitration Building & Real Estate

Offices — Algeria

Building

Mission details

Objectives

  • Report in response to the opposing expert on design and construction delays at the date of termination

Stakes

  • The general contractor presented a claim of €70.7M (eq.), or 141% of the initial contract amount
  • The Owner also filed counterclaims totalling €13.1M (eq.).

Results

The arbitrators confirmed that termination of the general contractor's contract was well founded and ordered the Owner to pay 11% of its claim.