Our expertise in action

Infrastructures de dessalement
Claim Management Environment & Urban Planning

Desalination Facilities

Desalination plant

Mission details

Context

For a company in charge of design, build and operate of a desalination plant: preparation of an extension of time claim

Mission

Claims management

Objectives

  • Delay analysis using the As planned vs As-built windows analysis methodology

Stakes

  • Time for Completion: 30 months
  • Contract amount: € eq. 146M
  • Extension of Time requested: 11 months

Result

Confidential

Aménagement parc paysager Sud de la France
Claim Management Environment & Urban Planning

Landscaped park development — Southern France

Landscaped park

Mission details

Context

After the claim for additional compensation was rejected at the general account stage, the small contractor referred the matter to the Administrative Court. Argos Construction's intervention as technical adviser alongside counsel helped secure €85k out of the €100k claimed.

Mission

Claim memorandum — draft final account

Objectives

  • Justification of additional works and time extension
  • Analysis of the impact on resource mobilisation
  • Establishment of cost-overrun and damages pricing

Stakes

  • 1-month time extension on an initial 5-month schedule
  • €100k of additional compensation on a €200k contract

Result

Administrative Court ruling: €85k