Industrial building + process — French Overseas
Industrial building
Mission details
Context
Numerous changes during design had generated a significant volume of additional studies, but the client felt the impact was confined to the detailed-design phase. Argos Construction's analysis demonstrated that the main impact was on the preliminary-design phase, justifying the full cost overruns and securing €1.2M of additional compensation on a €2.8M contract.
Mission
Claim for additional compensation — changes to the specifications
Objectives
- Impact of changes on preliminary studies
- Review and complement of cost-overrun pricing
Stakes
- 6-month extension of the preliminary design studies
- €1.2M of additional compensation on a €2.8M contract
Results
Settlement formalised by amendment for €1.2M