Metro Line
Smoke Extraction Ventilation of a Metro Line
Mission details
Context
In the context of a program to increase train capacity (from 26 m to 52 m) and modernize a metro line, a company was entrusted with the ventilation and smoke extraction works for 17 stations and 12 inter-station shafts, under an initial contract supplemented by an additional contract, for a total amount of €7.0 M excl. VAT.
The execution of the contract was severely disrupted by events beyond the contractor's control, including in particular the discovery of asbestos in stations and shafts, changes to safety standards imposed by State authorities, and multiple instances of late handovers. These disruptions resulted in a fundamental upset to the project's economics and significant delays to both partial and overall completion milestones.
Argos Construction acted as expert in support of Colas Rail in connection with its claim for additional compensation.
Mission
Claim Management
Objectives
- Analyse and quantify the external disruptions and their consequences on the contractor's schedule and costs;
- Demonstrate the fundamental upset to the project's economics, justifying the claim for additional compensation;
- Assess and value the additional costs arising from the disruptions and the acceleration measures proposed at the Client's request.
Stakes
- Total contract value: € 7.0 M excl. VAT (initial contract € 4.9 M + amendment no. 1 € 0.5 M + additional contract €1.6M)
- Initial overall completion period: 54 months;
- Delays justified by disruptions: 47.6 months on the overall completion period;
- Main disruptive events: discovery of asbestos in shafts and stations, modification of the system's safety level, late handovers (AGI cabinets, cable trays, electrical supplies), requests from the Quality Assurance Inspector (unit-by-unit commissioning, shaft throttling), additional works via 15 Variation Orders (€ 1.2M excl. VAT, representing 17% of the total contract value).