Office buildings — Southern France
Office buildings
Mission details
Context
On a painting contract where any change weighs directly on labour, late hand-over of work areas had stretched the schedule by 37% — but the team, inexperienced in contract management, could not substantiate it. Argos Construction's presentation of the claim convinced the Owner of the contractor's rigour and led to new contracts.
Mission
Preparation of a claim for additional compensation
Objectives
- Justification of work-window shifts caused by disruptions
- Establishment of cost-overrun and damages pricing
Stakes
- 3-month extension on an initial 8-month schedule
- €100k of additional compensation on a €300k contract
Results
Claim initially rejected. Assistance with case follow-up and management of forfeiture deadlines. Settlement negotiated at €60k