Our expertise in action

References

4 completed missions

Immeubles de Bureaux Sud de la France
Claim Management Building & Real Estate

Office buildings — Southern France

Office buildings

Mission details

Context

On a painting contract where any change weighs directly on labour, late hand-over of work areas had stretched the schedule by 37% — but the team, inexperienced in contract management, could not substantiate it. Argos Construction's presentation of the claim convinced the Owner of the contractor's rigour and led to new contracts.

Mission

Preparation of a claim for additional compensation

Objectives

  • Justification of work-window shifts caused by disruptions
  • Establishment of cost-overrun and damages pricing

Stakes

  • 3-month extension on an initial 8-month schedule
  • €100k of additional compensation on a €300k contract

Results

Claim initially rejected. Assistance with case follow-up and management of forfeiture deadlines. Settlement negotiated at €60k

Rénovation d'un complexe hôtelier
Claim Management Building & Real Estate

Hotel complex refurbishment

Building

Mission details

Context

The refurbishment of this high-end hotel complex is now expected to run 6.5 months late, due to numerous client changes and the failure of contractors holding key trade packages. The electrical contractor (€21M) engaged Argos Construction to prepare a provisional statement of cost overruns to support negotiations for an amendment.

Mission

Preparation of a provisional statement of cost overruns and damages

Objectives

  • Contractual and delay analysis
  • Review and complement of cost-overrun and damages pricing

Stakes

  • 6.5-month extension on an initial 21-month schedule
  • €3.8M of cost overruns

Results

Discussions ongoing

Réhabilitation d'un immeuble
Claim Management Building & Real Estate

Building refurbishment

Buildings

Mission details

Context

The conversion of this Parisian building into a 5-star hotel (€6M, 14 months) suffered a 7-month delay across all trades, entirely due to late input data and constant changes outside the joint venture's control. Argos Construction prepared the claim memorandum for €1.2M of cost overruns, while the Owner intends to apply €860k in delay penalties.

Mission

Preparation of a claim for additional compensation

Objectives

  • Analysis of contract documents and contemporaneous records
  • Analysis of cumulative delay impacts
  • Quantification of cost overruns and drafting of the memorandum

Stakes

  • 7-month delay on an initial 14-month schedule (+50%)
  • €1.2M on an initial €6M contract (20%)
Hôpital Sud de la France
Claim Management Building & Real Estate

Hospital — Southern France

Hospital

Mission details

Context

Following Argos Construction's intervention, which restored balance between the Owner and the contractor wrongly identified as the source of the delays on this multi-trade project, a claim for additional compensation could be presented and defended.

Mission

Claim for additional compensation — final account

Objectives

  • Reconstruction of disruptions and substantiation of the time extension
  • Analysis of impact on resource mobilisation
  • Establishment of cost-overrun and damages pricing

Stakes

  • 23-month time extension on an initial 25-month schedule
  • €0.8M of additional compensation on a €3M contract

Results

Time extension formalised (delay penalties lifted) and settlement at €0.4M